Building in the school summer holidays: your deadline is earlier than you think

Building in the school summer holidays: your deadline is earlier than you think

Every school estates manager knows the summer holiday is when the big jobs get done. What catches people out is how much of that holiday is actually available for building. At St Albans School this summer, we had eight weeks to create a new reception and visitor lounge. The real deadline wasn’t the first day of term. It was the day the school needed the space back.

The holiday isn’t all build time

On paper, a school summer holiday looks like a clear run. In practice, several things eat into it:

  • School set-up. Furniture, signage, equipment and displays usually go in after the builders leave, and need a finished, clean room.
  • Cleaning. A builder’s clean isn’t the same as a ready-to-use space. A deep clean needs its own time.
  • Staff returning early. Teachers and support staff are often back in school before pupils, and they need safe routes and working areas.
  • Snagging. Any small defects need fixing before the space is in daily use, not during the first week of term.

So when a school says “we’ve got the summer”, the first question we ask is: when do you actually need the keys back?

Plan back from the handover date

At St Albans, we built the programme backwards from the handover date. That one decision shaped everything else: when joinery had to be ordered, when the dusty work had to be finished, and when finishes and lighting went in.

In practice, that means:

  1. Fix the design before the holiday starts. Changes in week three of an eight-week job are what cause overruns. Layouts, finishes and power and data positions should be signed off before the site opens.
  2. Order long-lead items early. Bespoke joinery, glazed partitions and specialist lighting can have lead times longer than the holiday itself. If they’re ordered after the school breaks up, you’re already late.
  3. Agree positions early. Fix every power socket, data point and equipment position with the school at design stage, so nothing has to be moved later.
  4. Finish the dirty work first. Demolition, cutting and sanding are sequenced early, so dust is long gone before the finishes go on.

What we delivered at St Albans School

Designed by IID Architects, the new reception gives St Albans School the first impression it deserves. Full-height panelling with picture lights, painted radiator enclosures beneath oak window boards, a curved oak reception desk and a glazed meeting room come together in a space that feels calm, warm and built to last. See the full project in our St Albans School case study.

It was handed back on programme, ready for the start of term.

Planning summer works for next year?

The best time to plan a summer project is the autumn or spring before. That leaves time for design, approvals, pricing and ordering long-lead items before the holiday starts. If you’re a bursar or estates lead with a project in mind for summer 2027, get in touch and we’ll talk you through what’s realistic.

Frequently asked questions

Can a school refurbishment be done entirely in the summer holiday?
Often, yes, if the scope fits the time available and the design is fixed before the holiday starts. Larger projects may need phasing across more than one holiday, or some work during term time with the site safely separated.

When should a school start planning summer building work?
Ideally the autumn or spring before. That leaves time for design, any approvals, tendering and ordering long-lead items such as bespoke joinery and glazing.

How do you keep a summer project on programme?
We agree the handover date at the start and plan the programme back from it. The design is fixed and long-lead items are ordered before the holiday, so time on site is spent building, not waiting.

What happens if the work runs past the start of term?
That’s what the programme is there to prevent. If any work does have to continue, it needs a safe, separated work area and a plan agreed with the school before pupils return.

GET IN TOUCH

0800 043 2639

Eden Build UK Ltd

Unit 33, Woodside Industrial Estate,

Woodside, Thornwood, Epping,

Essex, CM16 6LJ

This field is for validation purposes and should be left unchanged.

Eden Build UK Ltd

Unit 33, Woodside Industrial Estate,

Woodside, Thornwood, Epping,

Essex, CM16 6LJ