JCT CONTRACTS FOR FIT-OUTS:
MINOR WORKS, INTERMEDIATE, OR DESIGN AND BUILD?

Author:
Mitchell Broughton, Operations Director, Eden Build.
Reviewed November 2026.

Most commercial fit-outs and refurbishments in England are let under a JCT contract. Choosing the right one matters more than people expect: it decides who carries design risk, how changes are priced and how much administration the job needs. This guide compares the three JCT contracts most used for fit-outs, and when each one fits.

The short answer

Contract Best for Who designs Typical fit-out use
Minor Works (MW / MWD) Simple, short works with full design information Client’s design team (MWD: contractor designs a defined part) Small refurbishments, single-floor Cat B, works without complex services
Intermediate (IC / ICD) Works of moderate complexity, fully designed, without highly complex services Client’s design team (ICD: contractor designs defined parts, often M&E) Most consultant-led fit-outs and refurbishments in the £500k–£4m range
Design and Build (DB) Projects where the client wants one party responsible for design and build Contractor completes the design from the client’s requirements Cat A, larger Cat B, or where the client has no design team

The Standard Building Contract (SBC) is used for larger, more complex projects, and is less common for fit-outs of this size.

Minor Works

Minor Works is short and straightforward to administer. It works well where the design is complete, the scope is simple, and there’s little specialist work. It’s less suited to jobs with significant M&E or several specialist packages, because it has fewer provisions for things like named subcontractors and detailed procedures for changes and delays.

The “with contractor’s design” version (MWD) lets the contractor design a defined part of the works.

Tidied-Modern-Office-Lounge

Intermediate

Intermediate is the workhorse for consultant-led fit-outs. It has fuller provisions than Minor Works for programme, extensions of time, loss and expense and named specialists, while staying manageable for a refurbishment of a few hundred thousand to a few million pounds.

ICD adds a contractor’s designed portion. On fit-outs this is often used for M&E, where the engineer produces a performance specification and the contractor’s specialist completes the detailed design.

Design and Build

Under Design and Build, the contractor takes responsibility for completing the design to meet the client’s requirements. It gives one point of responsibility and more price certainty early, but less control over detailed design, and changes after contract can be expensive.

It suits Cat A fit-outs, larger Cat B projects where the client wants a single point of contact, and clients without their own design team.

 

Fit-out points to watch

  • Landlord’s consent. Most fit-outs need a licence for alterations. Make sure the contract programme allows for it and for the landlord’s surveyor reviewing designs.
  • Cat A and Cat B interface. Where landlord and tenant works overlap, define clearly who does what and when.
  • Contractor’s design. If any design sits with the contractor, the employer’s requirements must say exactly what, and the contractor needs professional indemnity cover.
  • Edition. JCT publish new editions periodically. Make sure your documents and amendments use the current edition rather than a copy-and-paste of an old one.
  • Amendments. Heavily amended JCT contracts take longer to agree and price. Keep amendments to what the project genuinely needs.

Which should you use?

  • Design complete, simple scope, modest value: Minor Works
  • Design complete, consultant-led, moderate complexity: Intermediate
  • Design complete except M&E or other specialist parts: Intermediate with contractor’s design
  • One party responsible for design and construction: Design and Build

If you’re not sure, your QS or contract administrator will advise based on the design information you have and how much risk you want to keep.

How Eden work under JCT

Eden work under JCT Minor Works, Intermediate and Design and Build on commercial fit-outs and refurbishments. See JCT contractor and cost reporting and valuations for how we run valuations, variations and final accounts.

Which JCT contract is best for an office fit-out?

For a consultant-led fit-out with complete design information, the JCT Intermediate Building Contract is the most common choice. Minor Works suits simpler, smaller jobs, and Design and Build suits clients who want the contractor to carry the design.

What is the difference between JCT Minor Works and Intermediate?

Minor Works is shorter and simpler, for straightforward works with full design information. Intermediate has fuller provisions for programme, delays, loss and expense and named specialists, and suits more complex refurbishments.

What is a contractor's designed portion?

A defined part of the works, often M&E, that the contractor designs. It’s set out in the employer’s requirements and covered by the “with contractor’s design” versions of JCT contracts.

Can a fit-out be procured as design and build?

Yes. JCT Design and Build is often used for Cat A fit-outs and larger Cat B projects where the client wants one party responsible for design and construction.

Which JCT edition should we use?

The current edition of the relevant contract. Check your tender documents and any amendments refer to it rather than an older edition.

GET IN TOUCH

0800 043 2639

Eden Build UK Ltd
Unit 33, Woodside Industrial Estate,
Woodside, Thornwood, Epping,
Essex, CM16 6LJ

This field is for validation purposes and should be left unchanged.

Eden Build UK Ltd
Unit 33, Woodside Industrial Estate,
Woodside, Thornwood, Epping,
Essex, CM16 6LJ