office interior fit out cost uk Eden

HOW LONG DOES AN OFFICE
FIT OUT TAKE?

Author: Mitchell Brougton, Operations Director, Eden Build.
Reviewed August 2026.

Most people asking this question have a date in mind – a lease expiry, a term start, a board meeting where they have promised the new office will be ready. The useful answer is rarely the one they expect, because the build itself is usually the shortest and most predictable part of the whole thing.

A straightforward office fit out takes somewhere between eight and fourteen weeks on site. But the full programme, from first brief to the day people sit down at their desks, commonly runs five to eight months. The gap between those two numbers is where projects go wrong.

This guide sets out realistic durations by project size, breaks the programme into its three real phases, and explains which stages genuinely cause delay. It is written from the contractor’s side: these are the timescales Eden works to on projects between £100,000 and £4m.

Office-Fit-Out-London

The short answer

Project Time on site Full programme, brief to handover
Light refurbishment or single floor refresh, under 2,000 sq ft 2 – 6 weeks 8 – 14 weeks
Standard Cat B fit out, 2,000 – 5,000 sq ft 6 – 10 weeks 16 – 24 weeks
Mid-size fit out, 5,000 – 15,000 sq ft 8 – 14 weeks 20 – 34 weeks
Large or multi-floor scheme, 15,000 sq ft+ 14 – 26 weeks 30 weeks – 12 months
Cat A fit out (landlord works) 6 – 12 weeks 12 – 20 weeks

Two things to take from this table. First, the on-site figure is the one contractors quote and the one clients remember – and it is roughly a third of the real answer. Second, the ranges widen fast with size, because larger projects carry more approvals, more stakeholders and more long-lead items, not simply more square footage.

Commercial Fit out

The three phases

An office fit out is not one process. It is three, and only the last one happens on site.

1. Brief and design — 4 to 12 weeks

Space planning, layout, specification and costing. For a clear brief on a simple space this can be three or four weeks. For a multi-department business with several decision-makers it routinely takes three months, and most of that is not drawing time — it is waiting for decisions.

Every round of revisions adds one to two weeks. Businesses with a single empowered decision-maker move measurably faster than committees.

2. Approvals and procurement — 4 to 12 weeks, overlapping

This is the phase people forget, and it is where most programmes slip.

  • Licence to Alter. If you lease the building, your landlord must approve the works. Allow four to twelve weeks. It is administrative, largely outside your control, and it must be started early.
  • Building Regulations. Applies to almost every fit out — fire safety, means of escape, accessibility, ventilation, energy performance. Runs in parallel with design.
  • Long-lead procurement. Standard products arrive in four to six weeks. Bespoke joinery, specialist glazing, feature lighting and imported furniture can take twelve to sixteen. Furniture in particular is the most common single cause of a delayed move-in date.

Approvals and procurement can run alongside late-stage design, which is why an experienced contractor will push to identify long-lead items before the design is fully signed off.

3. On site — 2 to 26 weeks

The construction phase, in rough sequence: strip-out and enabling works, first-fix mechanical and electrical, partitioning, ceilings, second-fix M&E, joinery and finishes, flooring and decoration, commissioning, snagging and handover.

Mechanical and electrical is usually the critical path. Commissioning and testing sit at the end and cannot be compressed much — allow one to two weeks, and do not let anyone plan a move-in for the day after practical completion.

Shoreditch-4

What actually causes delay

In our experience, delays cluster in five places, and only one of them is the build:

  1. Late decisions. Finishes, furniture and AV choices made after the programme has started push procurement past the point where it can recover.
  2. Landlord approvals started too late. A Licence to Alter submitted a fortnight before the intended start date will not be back in time.
  3. Long-lead items ordered late. The programme is only as fast as its slowest delivery.
  4. Unforeseen building conditions. Asbestos, failing services, structural surprises. Older buildings hide more. A proper pre-start survey costs far less than the two to six weeks a surprise can add.
  5. Scope changes mid-build. The most expensive kind of change, in both money and time.

Note what is not on that list: bad weather, and the contractor working too slowly. Internal fit out is largely weather-independent, and the on-site phase is the most controllable part of the programme.

Office Fit Out - Russell Square

Working backwards from your date

If you have a fixed move-in date, count backwards rather than forwards. For a typical 5,000 sq ft Cat B fit out:

  • Month 1–2: brief, space planning, design development
  • Month 2–3: costing, contractor appointment, Licence to Alter submitted, long-lead items identified
  • Month 3–4: approvals returned, procurement placed, mobilisation
  • Month 4–6: on site
  • Final fortnight: commissioning, snagging, handover, IT and furniture installation

Start planning at least six months before you need to be in. If your lease expiry is driving the date, work back from that and add contingency — standard practice is ten to fifteen per cent on programme for simple projects and twenty to twenty-five per cent for complex ones.

BB37D7BF-A101-4A03-9BA4-88889E492E78

Refurbishing while the building is occupied

Timescales change when people are still working in the space, or when a school is still teaching. Occupied projects generally take longer overall but avoid the cost and disruption of decanting.

Phasing is the mechanism: the works are broken into zones, each completed and handed back before the next begins. Noisy operations move to evenings and weekends. Access, dust and fire escape routes are managed daily around the occupier.

Eden delivered a phased refurbishment across three occupied floors of the Civic Centre at The Water Gardens, Harlow — 12,000 sq ft, with council staff working throughout. Our school projects follow the same logic, compressed into the summer holidays with a hard, immovable deadline at the start of term.

If your project is in a live environment, expect a longer programme and a more detailed one. That is not inefficiency; it is what protects the people still using the building.

0Q0A2495

Can a fit out be done faster?

Yes, within limits. The genuine levers are:

  • Design and build procurement. A single contract for design and construction lets the two overlap rather than run in sequence. This is usually worth three to six weeks.
  • Early contractor involvement. Bringing the builder in during design catches buildability and lead-time problems while they are still cheap to fix.
  • Advance procurement. Ordering long-lead items before the full design is signed off.
  • Shift working. Evening and weekend shifts can compress the on-site period substantially, at a labour premium. On a project where delay carries a real cost — a lease running out, a term starting — it often pays for itself.

What does not work is compressing the design and approvals phase. That is where the time appears to be free, and it is the phase whose shortcuts show up as expensive variations later.

If someone offers you a full fit out from blank brief to occupation in eight weeks, ask specifically what they have left out.

How long does a Cat A fit out take?

Typically six to twelve weeks on site for a standard floor, with twelve to twenty weeks for the full programme including design and approvals. Cat A is more predictable than Cat B because the specification is largely standardised.

How far in advance should we start planning?

At least six months before your target move-in date for a mid-size project, and longer if your space needs structural alteration or you are taking a building in shell and core condition. Starting early costs nothing; starting late costs either your date or a premium to compress the works.

What is the longest part of an office fit out?

Usually design and approvals, not construction. Landlord Licence to Alter and long-lead procurement are the two stages most likely to move your handover date.

Can we stay in the building during the works?

Often, yes, with phased delivery and out-of-hours working. It extends the overall programme but avoids relocation costs. It needs to be planned from the outset rather than added later.

Does the programme include furniture and IT?

Not always. Furniture, AV and IT are frequently procured separately and installed after practical completion. Confirm who is coordinating them and when they are scheduled — a finished office with no desks is not a finished office.

What happens if the project overruns?

Under a JCT contract there are agreed mechanisms for extensions of time and, where the delay is the contractor’s, liquidated damages. More usefully: a weekly programme review with a contractor who tells you early is worth more than any contractual remedy.

Working to a fixed date? Send us your floor plans and your deadline. We will tell you honestly whether it is achievable and what it would take.

Call 0800 043 2639 or email [email protected].

GET IN TOUCH

0800 043 2639

Eden Build UK Ltd
Unit 33, Woodside Industrial Estate,
Woodside, Thornwood, Epping,
Essex, CM16 6LJ

This field is for validation purposes and should be left unchanged.

Eden Build UK Ltd
Unit 33, Woodside Industrial Estate,
Woodside, Thornwood, Epping,
Essex, CM16 6LJ