St Albans School wanted a reception that makes the right first impression on parents, visitors and prospective families, and sits naturally in a historic building. All of it had to happen over the summer break: eight weeks, a fixed handover date, and original brickwork and windows to work around.
Working to IID Architects‘ design, Eden planned the programme back from the handover date. The finished space includes:
Joinery and glazing were the long-lead items, so they were ordered early. Trades were sequenced so the dusty work was done early, leaving time for finishes, cleaning and snagging.
The new reception was handed over on programme, ready for the start of term. Visitors now arrive into a bright, panelled space with warm oak joinery, soft layered lighting and natural light from the original windows. It’s a first impression that matches the school’s standing.