This page sets out exactly what Eden provide on cost: what’s in our monthly report, how we substantiate a valuation, how we handle variations, and how we close out the final account. It’s the same on every project, whether we’re appointed under JCT Minor Works, Intermediate or Design and Build.

What you get each month

Every month, alongside our payment application, you receive a cost report in the same format from start to finish. It covers:

Line What it shows
Contract sum The agreed tender figure, unchanged
Approved variations Each instructed variation, its agreed value and instruction reference
Pending variations Instructed but not yet agreed, with our submitted price
Potential variations Changes raised but not yet instructed, with an order-of-cost
Provisional sums Allowance, spent to date and forecast remaining, per sum
Risk and early warnings Anything that could move the number, raised as soon as we see it
Anticipated final account Contract sum plus all of the above, with movement since last month
Cash flow Forecast against actual, so the client can plan funding

The point of the report is that nothing reaches the final account that you haven’t already seen in a monthly report.

Interim valuations you can actually check

We submit applications before the valuation date set in the contract, not on it. Each one is mapped to the contract sum analysis or activity schedule you issued at tender, so you’re measuring against your own document, not ours.

Substantiation comes with the application, not after you’ve asked for it:

  • Progress per package against the contract sum analysis
  • Dated site photos for each area claimed
  • Materials on site, and materials off site only with vesting documentation and insurance
  • Variation and provisional sum values tied to their instruction references

We respect the payment and pay less notice dates under the contract and the Construction Act. If your valuation differs from our application, we’d rather sit down and walk the site with you than argue by email.

Variations

We don’t proceed with changes on a verbal instruction. Where a change is needed, we:

  1. Raise it in writing as soon as we spot it, with the reason and the drawing or RFI it comes from.
  2. Price it against the contract rates, or build-up where no rate applies.
  3. Wait for the contract administrator’s written instruction before starting, unless it’s a safety matter.
  4. Log it in the variation register, which you see every month.

Daywork is used only where it’s genuinely the right route and agreed in advance, with sheets signed daily.

Working with the design team

Most of our refurbishment work is architect-led, with a QS, M&E engineer and structural engineer alongside. We track every RFI and design query in Procore, so the design team can see what’s outstanding and when it’s needed to hold the programme. Our cost control and purchasing run on LiveCosts, so committed cost is visible against budget per package as the job goes.

Where a design change would affect cost or programme, we tell the architect and QS together, with the impact, before it’s drawn up — not when the invoice arrives.

Closing the final account

Because variations are agreed as we go, the final account should be a check, not a negotiation. Our target is to submit a fully substantiated final account within 4 weeks of practical completion and agree it within 4 weeks. Retention is released in line with the contract at practical completion and at the end of the rectification period.

Most of our London work runs this way — see commercial refurbishment in London.

Questions to ask any contractor about cost reporting

When you’re building a tender list, these are worth asking at interview:

  1. Can we see a sample monthly cost report from a live project?
  2. How do you substantiate interim applications?
  3. Do you ever proceed on a verbal instruction?
  4. How long did your last three final accounts take to agree?
  5. Can we speak to the QS on one of those projects?

We’re happy to answer all five.

How often does Eden report on cost?

Monthly, with every payment application. The report uses the same format from start to finish and shows the contract sum, variations, provisional sums, risks and the anticipated final account.

How are interim valuations substantiated?

Each application is mapped to the contract sum analysis or activity schedule issued at tender, with dated site photos, materials evidence and instruction references for every variation and provisional sum claimed.

How do you price variations?

Against the contract rates, or a transparent build-up where no rate applies. We submit the price before starting and wait for a written instruction, except where safety requires immediate action.

Will you price our bill of quantities or contract sum analysis as issued?

Yes. We price the tender documents in the format issued and raise any queries before we price, not after award.

How long does it take to agree the final account?

Because variations are agreed month by month, the final account should be a check rather than a negotiation. We aim to submit a fully substantiated final account within two months of practical completion — well inside the three to six months JCT contracts normally allow.